Concrete Calculator

Work out how much concrete to order for a slab, wall, footing, round column or circular pad. The calculator gives cubic yards for a ready-mix order and the number of 60 lb or 80 lb bags if you plan to mix it yourself.

%

Concrete needed

1.36 cubic yards

  • Cubic feet36.7 ft³
  • Cubic meters1.04 m³
  • 80 lb bags62 bags
  • 60 lb bags82 bags
  • Approx. weight2.8 tons

Estimates only. Round up when you order, and confirm structural details with your local building code.

How to use it

  1. Pick the shape: a rectangle covers slabs, walls and footings; the round options cover post holes, columns and circular pads.
  2. Enter the dimensions. Each box has its own unit, so you can type the slab in feet and the thickness in inches.
  3. Set how many identical pours you have — for example 12 deck-pier holes.
  4. Keep a 5–10% waste allowance for uneven subgrade, spillage and form bulge.

The formula

Rectangle: volume = length × width × thickness

Circle: volume = π × (diameter ÷ 2)² × depth

Cubic yards = cubic feet ÷ 27

Bags = cubic feet ÷ bag yield (80 lb = 0.60 ft³, 60 lb = 0.45 ft³)

Worked example

ShapeSlab / wall / footing (rectangle)
Length10 ft
Width10 ft
Thickness / depth4 in
Quantity1
Waste / spillage allowance10 %

Result

Concrete needed1.36 cubic yards
Cubic feet36.7 ft³
Cubic meters1.04 m³
80 lb bags62 bags
60 lb bags82 bags
Approx. weight2.8 tons

Tips before you order

  • Ready-mix trucks carry about 10 yd³; below that most plants add a short-load fee per yard.
  • A 4 in slab uses 1.23 yd³ per 100 ft². A 6 in slab uses 1.85 yd³ per 100 ft².
  • For more than about one cubic yard, ready-mix is usually cheaper and faster than bags.
See typical concrete prices for every state on the concrete prices by state page.

Questions

How many bags of concrete are in a yard?

About 45 bags of 80 lb, 60 bags of 60 lb, or 90 bags of 40 lb premix make one cubic yard (27 ft³).

How thick should a concrete slab be?

4 in is standard for patios, walkways and garage floors that carry cars. Use 5–6 in for heavier vehicles, RVs or hot tubs, and follow any engineered plans.

Should I order extra concrete?

Yes. Running short mid-pour leaves a cold joint. Most contractors order 5–10% over the calculated volume.